Managerial Competence for Optimization of Variations with Public Construction Projects: A Case of Selected Public Procuring Entities in Mbeya, Tanzania

Received: 20 June 2022     Accepted: 8 July 2022     Published: 24 August 2022
Views:       Downloads:
Abstract

The study aimed at investigating on the effects of managerial competence towards optimization of project deliverable variations. The investigation was carried out following a number of cases reported over >75% of public projects not to be completed on time and if completed then they found not of the quality intended. There are number of factors which count for this dilemma such as budget constraints, technical incompetence, dishonest, force majeure and managerial incompetence. Managerial incompetence being one among other influencing factors was a point of focus contributing in fulfilling the gap. To explicitly reveal to what extent this managerial proficiencyover project follow-up, monitoring and evaluation lead to performance of the project to the standards expected then quantitative research approach, descriptive-survey design and simple random sampling were employed. The target population being technicians, engineers, contractors, architects in construction industry in Mbeya, Tanzania then reality was revealed. From 230 unit of inquiry while the facts collected using questionnaireand throughthe use of structural equation modeling (by applying the descriptive statistics, correlation, average variance explained and multiple regression) it was found that project follow up, monitoring and evaluation managerial competences contribute positively and statistical significant on optimization of variations ofend deliverables. It is from this positivism between variables revealed what this study recommends that the project managers have to ensure effective follow-up, monitoring and evaluation of the public construction projects in-order to optimize the variations over end deliverables effectively and most significantly.

Published in American Journal of Management Science and Engineering (Volume 7, Issue 4)
DOI 10.11648/j.ajmse.20220704.13
Page(s) 51-58
Creative Commons

This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited.

Copyright

Copyright © The Author(s), 2022. Published by Science Publishing Group

Keywords

Project, Follow up, Monitoring, Evaluation, Project Deliverable Variations

References
[1] Johnsen, H. (2019). Scientific Assessment of TSCV-Retrieval from Stereo-Sar-Retrieval Algorithm.
[2] Mirkin, B. (2019). Core Data Analysis: Summarization, Correlation, and Visualization. Cham: Springer International Publishing.
[3] Dalcher, D. (2019). Moving beyond project delivery: Reflecting on the life cycle concept as way for organising project work. PM World Journal, 8.
[4] Gálvez, E. D., Ordieres, J. B., & Capuz-Rizo, S. F. (2020). Evaluation of project duration uncertainty using the dependency structure matrix and Monte Carlo simulations. Journal of Construction, 14 (2), 72-79.
[5] El Esawey, M. (2020). Using spatio-temporal data for estimating missing cycling counts: a multiple imputation approach. Transportmetrica A: transport science, 16 (1), 5-22.
[6] Yan, Y., Chen, S., Nie, Y., & Xu, Y. (2020). Characterization of volatile sulfur compounds in soy sauce aroma type Baijiu and changes during fermentation by GC× GC-TOFMS, organoleptic impact evaluation, and multivariate data analysis. Food Research International, 131, 109043.
[7] Black, W., & Babin, B. J. (2019). Multivariate data analysis: Its approach, evolution, and impact. In The Great Facilitator (pp. 121-130). Springer, Cham.
[8] Ghauri, P., Grønhaug, K., & Strange, R. (2020). Research methods in business studies. Cambridge University Press.
[9] Deeks, J. J., Higgins, J. P., Altman, D. G., & Cochrane Statistical Methods Group. (2019). Analysing data and undertaking meta-analyses. Cochrane handbook for systematic reviews of interventions, 241-284.
[10] Razali, A. B. (2019). Self-Directed Learning Readiness (SDLR) among foundation students from high and low proficiency levels to learn English language. Malaysian Journal of Learning and Instruction, 15 (2), 55-81.
[11] Park, Y. S., Konge, L., & Artino Jr, A. R. (2020). The positivism paradigm of research. Academic Medicine, 95 (5), 690-694.
[12] Farashah, A. D., Thomas, J., & Blomquist, T. (2019). Exploring the value of project management certification in selection and recruiting. International Journal of Project Management, 37 (1), 14-26.
[13] Augenbroe, G. (2019). The role of simulation in performance-based building. Building performance simulation for design and operation.
[14] Parsons, S., Kruijt, A. W., & Fox, E. (2019). Psychological Science Needs a Standard Practice of Reporting the Reliability of Cognitive-Behavioral Measurements. Advances in Methods and Practices in Psychological Science, 2 (4), 378-395.
[15] Kerzner, H. (2019). Using the project management maturity model: strategic planning for project management. John Wiley & Sons.
[16] Lamesgin, A. (2019). Evaluation of Ethiopia Humanitarian Response Fund/HRF/Project Monitoring System (Doctoral dissertation, AAU).
[17] Asrat, M. (2018). The Role of Project Communication Management in improving project performance of building construction projects: A case study of Modcon Engineering PLC (Doctoral dissertation).
[18] Cleland, D., & Ireland, L. (2007). Project Management: Strategic Design and Implementation. (5th ed.). New York: McGraw-Hill.
[19] Coe, J. & Mayne, R. (2008). Is your campaign making a difference? NCVO. Transition Initiative workshop Measuring and Evaluating Resilience in Transition, Hamilton House, Stokes Croft,
[20] Bristol, P. (2012). Basics of Monitoring and Evaluation. Retrieved on 12nd December 2019 from http://www.transitionresearchnetwork.org/connected-communities.html.
[21] Gasasira, H. (2017). Project Planning Practices and Success of Agricultural Projects in Rwanda: A Case Study of Capacity Development for Agricultural Innovation Systems (cdais)’ Project in Nyagatare District (Doctoral Dissertation).
[22] Weyifen, D. (2018). Assessing the Importance of Project Planning, Monitoring and Evaluation on project success: A case study of Abune Gorgorios School Building Project (Doctoral dissertation, Addis Ababa University).
[23] Holgersson, H. (2006). A graphical method for assessing multivariate normality. Computational Statistics, 21 (1): 141–149 [p 151].
[24] Howell, G. & Koskela, L. (2001). Reforming project management: The role of lean construction. 8th Annual Conference of the International Group for Lean ConstructionIGLC-8. Brighton, 17 - 19 July 2000.
[25] Husson, J, Josse, S. & Mazet. F. J. (2014). Multivariate Exploratory Data Analysis and Data Mining with R. URL http://CRAN.R-project.org/package=FactoMineR.R package version 1.26. [p 151].
[26] JICA Guideline for Project Evaluation. (2004). Practical Methods for Project Evaluation, Planningand Coordination Department Japan International Cooperation Agency (JICA), Office of Evaluation and Post Project Monitoring, Planning and Evaluation Department, September: 1-25.
[27] Jiménez, A. & Pérez-Foguet, A. (2010). Challenges for Water Governance in Rural Water Supply: Lessons Learned from Tanzania. International Journal of Water Resources Development, 26 (2), 235–248.
[28] Kaula, S. (2019). Collaborative Procurement: A Treaky for small and medium local contractorswin the metallurgical procurement work opportunitiesadvertised in Tanzania. India, AARFS Publishing.
[29] Getachew, S. (2018). Monitoring And Evaluation Tools Affecting Project Performance: A Case Of Addis Ababa Network Of People Living With Hiv/Aids Associations (Anopa+) (Doctoral dissertation, Addis Ababa University).
[30] Khan, M. A. (2019). A Guidebook on Results Based Monitoring and Evaluation: Key Concepts, Issuesand Applications. Monitoring and Progress Re-view Division, Ministry of Plan Implementation, Government of Sri Lanka. Colombo, Sri Lanka.
[31] Lamb, B. (2011). Campaigning for change: Learning from the United States. Campaigning Effectiveness (London: NCVO), NCVO.
[32] Maimula, S. (2017). Challenges in practicing monitoring and evaluation: The Case of Local government water projects in Mkuranga, Tanzania. Open University of Tanzania.
[33] Mlinga, R. S. (2008). Ethics in Public Procurement: A Missing Link in the Education and Training of Construction Industry Practitioners. Proceedings of Construction Industry Forum, September 12-13, Dar es Salaam, Tanzania, 1-19.
[34] Newman, J. M., Martin, L. & Fantini, A. (2003). A System Dynamics Approach to Monitoring and Evaluation at the Country Level: An Application to the Evaluation of Malaria-Control Programs in Bolivia. World Bank, Washington, DC.
[35] Ointotwenty (2014). PERT/CPM Scheduling for Time/Cost Management. Retrieved October 25th 2015 from http://www.ointotwenty.com/services.htm.
[36] Erasmus, R. (2018). Monitoring and evaluation for the success of agricultural donor funded projects: a case study of rice growing project in cogirira cooperative in Bugesera District, Rwanda (doctoral dissertation).
[37] Schappe, J. (2005). Early childhood assessment: A correlational study of the relationships among student performance, student feelings, and teacher perceptions. Early Childhood Education Journal, 33 (3): 187–193.
[38] Schwaber, K. & Beedle, M. (2018). Agile Software Development with Scrum. Prentice Hall, Upper Saddle River. p 158.
[39] Mebratu, M. (2018). Regular Project Monitoring for Project Success: The Case of Input Voucher System Project in Ethiopia (Doctoral dissertation, Addis Ababa University).
[40] Stage, F. K. (2015). Reporting Structural Equation Modeling and Confirmatory Factor Analysis Results: A Review. USA; New York University.
[41] Leonard, H. (2018). Monitoring and Evaluation Success of Wash Project Under Global Humanitarian and Development Foundation (Doctoral Dissertation).
[42] Ernestine, N. (2018). The influence of monitoring and evaluation on project performance: a case of Africa indoor residual spraying (airs) (Doctoral dissertation, Mount Kenya University).
[43] Niyitanga, J. G. (2018). Monitoring practices and Success of Agricultural Projects: A Case Study of Bugesera Agricultural Development Support Project, Rwanda (Doctoral Dissertation).
[44] World Bank & Inter-American Development Bank. (2010). Challenges in Monitoring and Evaluating: An Opportunity to Institutionalize. Fifth Conference of the Latin America and the Caribbean Monitoring and Evaluation (M & E) Network. Washington, DC.
[45] Grace, N. (2018). Effectiveness of monitoring and evaluation on the project success a case study of agricultural rural sector support projects (rssp) in Muhanga district (Doctoral dissertation, Mount Kenya University).
Cite This Article
  • APA Style

    Kaula Stephen. (2022). Managerial Competence for Optimization of Variations with Public Construction Projects: A Case of Selected Public Procuring Entities in Mbeya, Tanzania. American Journal of Management Science and Engineering, 7(4), 51-58. https://doi.org/10.11648/j.ajmse.20220704.13

    Copy | Download

    ACS Style

    Kaula Stephen. Managerial Competence for Optimization of Variations with Public Construction Projects: A Case of Selected Public Procuring Entities in Mbeya, Tanzania. Am. J. Manag. Sci. Eng. 2022, 7(4), 51-58. doi: 10.11648/j.ajmse.20220704.13

    Copy | Download

    AMA Style

    Kaula Stephen. Managerial Competence for Optimization of Variations with Public Construction Projects: A Case of Selected Public Procuring Entities in Mbeya, Tanzania. Am J Manag Sci Eng. 2022;7(4):51-58. doi: 10.11648/j.ajmse.20220704.13

    Copy | Download

  • @article{10.11648/j.ajmse.20220704.13,
      author = {Kaula Stephen},
      title = {Managerial Competence for Optimization of Variations with Public Construction Projects: A Case of Selected Public Procuring Entities in Mbeya, Tanzania},
      journal = {American Journal of Management Science and Engineering},
      volume = {7},
      number = {4},
      pages = {51-58},
      doi = {10.11648/j.ajmse.20220704.13},
      url = {https://doi.org/10.11648/j.ajmse.20220704.13},
      eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.ajmse.20220704.13},
      abstract = {The study aimed at investigating on the effects of managerial competence towards optimization of project deliverable variations. The investigation was carried out following a number of cases reported over >75% of public projects not to be completed on time and if completed then they found not of the quality intended. There are number of factors which count for this dilemma such as budget constraints, technical incompetence, dishonest, force majeure and managerial incompetence. Managerial incompetence being one among other influencing factors was a point of focus contributing in fulfilling the gap. To explicitly reveal to what extent this managerial proficiencyover project follow-up, monitoring and evaluation lead to performance of the project to the standards expected then quantitative research approach, descriptive-survey design and simple random sampling were employed. The target population being technicians, engineers, contractors, architects in construction industry in Mbeya, Tanzania then reality was revealed. From 230 unit of inquiry while the facts collected using questionnaireand throughthe use of structural equation modeling (by applying the descriptive statistics, correlation, average variance explained and multiple regression) it was found that project follow up, monitoring and evaluation managerial competences contribute positively and statistical significant on optimization of variations ofend deliverables. It is from this positivism between variables revealed what this study recommends that the project managers have to ensure effective follow-up, monitoring and evaluation of the public construction projects in-order to optimize the variations over end deliverables effectively and most significantly.},
     year = {2022}
    }
    

    Copy | Download

  • TY  - JOUR
    T1  - Managerial Competence for Optimization of Variations with Public Construction Projects: A Case of Selected Public Procuring Entities in Mbeya, Tanzania
    AU  - Kaula Stephen
    Y1  - 2022/08/24
    PY  - 2022
    N1  - https://doi.org/10.11648/j.ajmse.20220704.13
    DO  - 10.11648/j.ajmse.20220704.13
    T2  - American Journal of Management Science and Engineering
    JF  - American Journal of Management Science and Engineering
    JO  - American Journal of Management Science and Engineering
    SP  - 51
    EP  - 58
    PB  - Science Publishing Group
    SN  - 2575-1379
    UR  - https://doi.org/10.11648/j.ajmse.20220704.13
    AB  - The study aimed at investigating on the effects of managerial competence towards optimization of project deliverable variations. The investigation was carried out following a number of cases reported over >75% of public projects not to be completed on time and if completed then they found not of the quality intended. There are number of factors which count for this dilemma such as budget constraints, technical incompetence, dishonest, force majeure and managerial incompetence. Managerial incompetence being one among other influencing factors was a point of focus contributing in fulfilling the gap. To explicitly reveal to what extent this managerial proficiencyover project follow-up, monitoring and evaluation lead to performance of the project to the standards expected then quantitative research approach, descriptive-survey design and simple random sampling were employed. The target population being technicians, engineers, contractors, architects in construction industry in Mbeya, Tanzania then reality was revealed. From 230 unit of inquiry while the facts collected using questionnaireand throughthe use of structural equation modeling (by applying the descriptive statistics, correlation, average variance explained and multiple regression) it was found that project follow up, monitoring and evaluation managerial competences contribute positively and statistical significant on optimization of variations ofend deliverables. It is from this positivism between variables revealed what this study recommends that the project managers have to ensure effective follow-up, monitoring and evaluation of the public construction projects in-order to optimize the variations over end deliverables effectively and most significantly.
    VL  - 7
    IS  - 4
    ER  - 

    Copy | Download

Author Information
  • Faculty of Business Management, Open University of Tanzania, Mbeya, Tanzania

  • Sections