Cost optimization is a process that should be carried out throughout the construction period to ensure that the cost of the project is within an allotted budget. Time and cost are the two most significant factors in any construction project. Cost increases with the time of construction. The objective of this study was to find out the factors that contribute to the optimization of construction costs in building construction projects in Nepal. The study was conducted during the period from April 2019 to September 2020. Field observation, in-depth interviews, focus group discussions and questionnaire surveys were the major tools for the investigation of this study. The findings were analyzed in nine categories: project related factors, design related factors, owner related factors, consultant related factors, contractor related factors, material related factors, labor related factors, equipment related factors, and external factors. The study found some key factors related to time and cost overrun, optimizing cost of construction and the strategies to optimize project costs. The most important strategy to optimize the construction cost are effective cost planning and control, development of proper monitoring and tracking system, sound working environment, recording daily work progress, using time cost trade off, follow plan-do-check-act quality policy, hire skilled labor and effective supervision. The study suggests that constructability and value engineering principles should be adopted in construction projects.
Published in | American Journal of Science, Engineering and Technology (Volume 6, Issue 1) |
DOI | 10.11648/j.ajset.20210601.12 |
Page(s) | 8-19 |
Creative Commons |
This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited. |
Copyright |
Copyright © The Author(s), 2021. Published by Science Publishing Group |
Cost Optimization, Time Overrun, Cost Overrun, Constructability and Value Engineering
[1] | Sabanna, Shivaraj, 2015. “Cost optimization in select consumer product sector companies in India”, PHD thesis http://hdl.handle.net/10603/57248, Gulbarg University. |
[2] | Elbeltagi, E. 2009. Lecture Notes on Construction Project Management, Structural Engineering Department, Faculty of engineering, Mansoura University, Egypt. |
[3] | Khan, R. A. (2008), Role of Construction Sector in Economic Growth: Empirical Evidence from Pakistan Economy, conference paper, First International Conference on Construction In Developing Countries (ICCIDC–I)“Advancing and Integrating Construction Education, Research & Practice” August 4-5, 2008, Karachi,, Pakistan, page 279-278. |
[4] | Baral, S, 2009 “Nepalese Construction Industry: Challenges “...santoshbaral.blogspot.com› 2009/12› Nepalese-construction-industry. |
[5] | Economic Survey 2017/18. Government of Nepal. Ministry of Finance. Singh Durbar, Kathmandu...Sep 14, 2018, page 10. |
[6] | FCAN, 2012. Construction Industry in Nepal. [Federation of Contractors association Nepal] Available at: http://www.fcan.org/np/pages.php?pid=83. [Last Accessed Jun 11– 2016]. |
[7] | KERZNER HAROLD, Ph. D, 2003, project Management, “A Systems Approach to Planning, Scheduling, and Controlling”, EIGHTH EDITION, Division of Business Administration, Baldwin-Wallace College, Berea, Ohio. |
[8] | Chitrakar, M., 2005. Time overrun in Building Construction project in Nepal. MSc. Nepal Engineering College –CPS, Pokhara University. |
[9] | Basaula, P. R. (2015), “Time-Cost Optimization of Construction Operation: A case study on building construction project of CTEVT, Nepal”, Master of Science in Engineering Managaement, Acme Engineering college, Purbanchal University, Nepal. |
[10] | Lester, A. (2000) Project Planning and Control, Butterworth-Heinemann, Oxford. |
[11] | Nicholas, J. (2001) Project Management for Business and Technology, Prentice Hall, Upper Saddle River, NJ. |
[12] | Rajguru, Anuja, & Mahatme, Parag. (March 2016) “Effective Techniques in Cost Optimization of Construction Project” International Journal of Research in Engineering and Technology Vol. 4, pp. 464-469. |
[13] | Sambasivan, M., & Soon, Y. W. (2007), “Causes and effects of delays in Malaysian construction industry”. International Journal of Project Management, 25 (5), 517-526. |
[14] | Sah, Tumi, Omran, A., Pakir, AHK (2009), “Causes of delay in Construction Industry in Libya”. Proc. Int. Conf. Administration and Business, Univ. Bucharest, Romania, 14-15th November 2009. pp. 265-272. |
[15] | Mahadik U. A. (2015), “Cost Reduction in Construction Projects” www.ijetmas.com September 2015, Volume 3, Special Issue, ISSN 2349-4476, page-397. |
[16] | Savithra, M. N. and Amutha, M. (2019),”Cost Simulation in an Item Based Project Involving Construction Engineering and Management”, www.ijirset.com Vol. 8, Issue 3, March 2019. |
[17] | NgS. & Zhang Y. (2008), “Optimizing Construction Time & Cost using Ant Colony Optimization Approach” Jr. Construction EM. (ASCE). |
[18] | Kashid P. M. &Jamgade M. (2019), “Time and cost optimization of construction projects: A review”, ISSN: 2277-9655, http://www.ijesrt.com© International Journal of Engineering Sciences & Research Technology. |
[19] | Gomer, J. E., Hass, C. T. and Morton, D. P. (2002),”Assignment and Allocation Optimization of Partially Multi skilled Workforce". Journal of Construction Engineering and Management/March/April 2002, ASCE. |
[20] | Asamoah, R. O., Ankrah, J. S., Nyako, K. O. and Tutu, E. O. (2016), “Cost Analysis of Precast and Cast-in-Place Concrete Construction for Selected Public Buildings in Ghana” Hindawi Publishing Corporation Journal of Construction Engineering Volume 2016, Article ID 8785129. |
[21] | Rajguru, Anuja and Mahatme Parag (2015). “Effective techniques in cost optimization of construction project”. IJIFR/ V3/ E5/ 03. |
[22] | Samuel, J. J. (2015),” Cost effective methods used in various levels of a building”, International Journal of Engineering Research and General Science Volume 3, Issue 6, November-December, 2015, pp. 850-854. |
[23] | Mishra AK, Bhandari S. Performance Assessment of Ongoing Construction Projects under Town Development Fund, Nepal, Int j Adv Res Civil Stru Engr 2018; 1 (1&2): 27-39. |
[24] | Maskey, Ajit and Mishra, A. K., 2018. “Labor productivity assessment of armed police force Nepal building construction projects”, International Journal of Current Research, 10, (11), December, 2018. |
[25] | Chilwal K. and Mishra A. K., 2018. Impact of Performance on profitability of small hydropower projects in Nepal, International Journal of Current Research, 10 (1). pp. 63918-63925. |
[26] | HEIZER, J.; RENDER, B. (1996) Production & Operations Management: strategic and tactical decisions. 4th Edition. USA, New Jersey: Prentice Hall. |
[27] | TAMRAKAR, P. (2013) Analysis and Improvement by the Application of Network Analysis (Pert/CPM). The International Journal of Engineering and Science, v. 2, n. 1, pp. 154-159. |
[28] | Dania, A. A., Kehinde, J. O. and Bala, K. (2007),”A study of construction material waste manaagemet practices by construction firms in Nigeria”, www.irb.fraunhofer.de. |
[29] | Wan, Michele (2018),” Eight Key Strategies to Reduce Cost in the Construction Sector” PDPM. www.sipmm.org.sg. |
[30] | @easyprojects.net, 1120 Finch Avenue West, Suite 201, Toronto, Ontario, M3J 3H7 Canada. |
[31] | Glavinich, T. E., (1995), “Improving Constructability during Desihn phase”, J. of Architectural Eng., Vol 1., No. 2, 73-76. |
[32] | Elsonosi, H. (2000),” Intelligent Computer System for Exchanging Value Engineering in the Egyptian Industry”, AUC, p. 72; 2000. |
[33] | Zimmerman LW, and Hart GD.(1982),” Value Engineering, A Practical Approach for Owners, Designers and Contractors”, Van Nostr and Reinhold Company, Inc., New York, 1982. |
[34] | Abidin N, Pasquire C. (2003) “Moving towards sustainability through value management. In: Proceedings of the joint international symposium of CIB working commissions W55, W65 and W107”, Singapore, Vol. 2, pp. 258-268; 2003. |
[35] | Mohamed, S. (2015), Integrating Value Engineering and Facility Management as an Approach to Face Risks, Master Thesis, Ain Shams University, Architecture Department (2015). |
[36] | Khodeir, L. M. and Ghandour, A. E., 2018, “Examining the role of value management in controlling cost overrun [application on residential construction projects in Egypt]” https://doi.org/10.1016/j.asej.2018.11.008. |
[37] | Rane, N. L., 2016, “Application of value engineering techniques in building construction projects”, www.ijesrt.com. |
APA Style
Surendra Kumar Karn, Khet Raj Dahal. (2021). Cost Optimization in Building Construction Projects with Special Reference to Kathmandu Valley of Nepal. American Journal of Science, Engineering and Technology, 6(1), 8-19. https://doi.org/10.11648/j.ajset.20210601.12
ACS Style
Surendra Kumar Karn; Khet Raj Dahal. Cost Optimization in Building Construction Projects with Special Reference to Kathmandu Valley of Nepal. Am. J. Sci. Eng. Technol. 2021, 6(1), 8-19. doi: 10.11648/j.ajset.20210601.12
AMA Style
Surendra Kumar Karn, Khet Raj Dahal. Cost Optimization in Building Construction Projects with Special Reference to Kathmandu Valley of Nepal. Am J Sci Eng Technol. 2021;6(1):8-19. doi: 10.11648/j.ajset.20210601.12
@article{10.11648/j.ajset.20210601.12, author = {Surendra Kumar Karn and Khet Raj Dahal}, title = {Cost Optimization in Building Construction Projects with Special Reference to Kathmandu Valley of Nepal}, journal = {American Journal of Science, Engineering and Technology}, volume = {6}, number = {1}, pages = {8-19}, doi = {10.11648/j.ajset.20210601.12}, url = {https://doi.org/10.11648/j.ajset.20210601.12}, eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.ajset.20210601.12}, abstract = {Cost optimization is a process that should be carried out throughout the construction period to ensure that the cost of the project is within an allotted budget. Time and cost are the two most significant factors in any construction project. Cost increases with the time of construction. The objective of this study was to find out the factors that contribute to the optimization of construction costs in building construction projects in Nepal. The study was conducted during the period from April 2019 to September 2020. Field observation, in-depth interviews, focus group discussions and questionnaire surveys were the major tools for the investigation of this study. The findings were analyzed in nine categories: project related factors, design related factors, owner related factors, consultant related factors, contractor related factors, material related factors, labor related factors, equipment related factors, and external factors. The study found some key factors related to time and cost overrun, optimizing cost of construction and the strategies to optimize project costs. The most important strategy to optimize the construction cost are effective cost planning and control, development of proper monitoring and tracking system, sound working environment, recording daily work progress, using time cost trade off, follow plan-do-check-act quality policy, hire skilled labor and effective supervision. The study suggests that constructability and value engineering principles should be adopted in construction projects.}, year = {2021} }
TY - JOUR T1 - Cost Optimization in Building Construction Projects with Special Reference to Kathmandu Valley of Nepal AU - Surendra Kumar Karn AU - Khet Raj Dahal Y1 - 2021/04/26 PY - 2021 N1 - https://doi.org/10.11648/j.ajset.20210601.12 DO - 10.11648/j.ajset.20210601.12 T2 - American Journal of Science, Engineering and Technology JF - American Journal of Science, Engineering and Technology JO - American Journal of Science, Engineering and Technology SP - 8 EP - 19 PB - Science Publishing Group SN - 2578-8353 UR - https://doi.org/10.11648/j.ajset.20210601.12 AB - Cost optimization is a process that should be carried out throughout the construction period to ensure that the cost of the project is within an allotted budget. Time and cost are the two most significant factors in any construction project. Cost increases with the time of construction. The objective of this study was to find out the factors that contribute to the optimization of construction costs in building construction projects in Nepal. The study was conducted during the period from April 2019 to September 2020. Field observation, in-depth interviews, focus group discussions and questionnaire surveys were the major tools for the investigation of this study. The findings were analyzed in nine categories: project related factors, design related factors, owner related factors, consultant related factors, contractor related factors, material related factors, labor related factors, equipment related factors, and external factors. The study found some key factors related to time and cost overrun, optimizing cost of construction and the strategies to optimize project costs. The most important strategy to optimize the construction cost are effective cost planning and control, development of proper monitoring and tracking system, sound working environment, recording daily work progress, using time cost trade off, follow plan-do-check-act quality policy, hire skilled labor and effective supervision. The study suggests that constructability and value engineering principles should be adopted in construction projects. VL - 6 IS - 1 ER -